Nurses Station is nearly complete

Major sections like the Nurses Station, the flat roofs over the Care Center, and main hallways are nearly complete. The wall between the ER and the ER garage has also been installed and is coming together.

The junction at the entrance into the Care Center and Hospital is coming together.

The junction at the entrance into the Care Center and Hospital is coming together.

junction2

The Nurses Station has been installed and is almost complete.

The Nurses Station has been installed and is almost complete.

ns2

A new hallway is open and ready to be used.

A new hallway is open and ready to be used.

All of the rooms have been taped and sheetrocked.

All of the rooms have been taped and sheetrocked.

The flat roof over the Care Center is complete.

The flat roof over the Care Center is complete.

Painting and roofing starting this week

Eight patient rooms are almost ready to be occupied as of this week, but won’t be until the ER is completed. The temporary roof was pulled back early this week in preparation for roofers.

Once the wall comes down, this hallways will be ready for use.

Once the wall comes down, this hallways will be ready for use.

021

Care Center rooms have been sheetrocked.

Care Center rooms have been sheetrocked.

Plumbing rough-ins have been created for the kitchen area of the 200 wing.

Plumbing rough-ins have been created for the kitchen area of the 200 wing.

The temporary roof has been pulled back for the roofers.

The temporary roof has been pulled back for the roofers.

Eight rooms like this are almost completed.

Eight rooms like this are almost completed.

New floors and studs in place.

New floors and studs in place.

Eight patient rooms nearly completed

With March rolling in, it’s out with the old and in with the new emergency department. The floors have been dug up and there’s a wide-open space ready for more progress. Eight patient rooms are almost ready to go, but they will not be used until all the patient rooms and the emergency department is complete.

Almost eight rooms similar to this are completed.

Almost eight rooms similar to this are completed.

059

Some of the walls are now painted in the hallways, offices, and exam areas.

Some of the walls are now painted in the hallways, offices, and exam areas.

The Care Center 200 Wing now has door frames and plumbing tie ins ready for the next step.

The Care Center 200 Wing now has door frames and plumbing tie ins ready for the next step.

The old maintenance shop and kitchen have been dug up and will turn into the emergency department and garage.

The old maintenance shop and kitchen have been dug up and will turn into the emergency department and garage.

Door frames stacked, waiting for walls!

Door frames stacked, waiting for walls!

The floors have been dug up and plumbing tie ins have been made in the new emergency department and the emergency drive-thru.

The floors have been dug up and plumbing tie ins have been made in the new emergency department and the emergency drive-thru.

Ceilings installed and walls prepped

Studs are being placed in preparation for wall installation. The old maintenance room and kitchen is nearly empty so the crew can start transforming it into the new ER and patient rooms.

The crew is starting to stand up studs for wall installation.

The crew is starting to stand up studs for wall installation.

016 033

Ceiling tiles have been installed.

Ceiling tiles have been installed.

The OR and the scope cleaning room are taking shape.

The OR and the scope cleaning room are taking shape.

The maintenance shop is almost cleared out to become the new ER with three patient rooms.

The maintenance shop is almost cleared out to become the new ER with three patient rooms.

Walls are going up and the Nurses Station is going down

The layout is getting more and more apparent each week, especially with more structures appearing this week. The Nurses Station and the old kitchen is cleared out to be remodeled.

Demo began in the old Nurses Station to be reduced and remodeled.

005 008

Nurses Station starting to take shape.

044 082

Scaffolding has been put up in the OR.

020

Grab bars and nurse call stations have been installed into the patient bathrooms.

077

Walls have been put into the hallway entering the hospital.

073 068 062

Structures are taking shape!

Drywall and door frames are going up, allowing staff to visualize what the inside of the hospital will look like!

The door frames of the doors leading into the hospital are installed.

The door frames of the doors leading into the hospital are installed.

Progress is being made on the hallway and patient rooms.

Progress is being made on the hallway and patient rooms.

Walls have been stood up and MEP rough-in has started.

Walls have been stood up and MEP rough-in has started.

Care Center 200 hall is coming together.

Care Center 200 hall is coming together.

The central area will be the outreach clinic space.

The central area will be the outreach clinic space.

Hallways and offices are taking shape

Fast progress is happening seemingly overnight at the new hospital. Hallways are shaping up to look like hallways and bathroom structures are being installed.

 

Care Center 200 wing is getting tied into the old building. Drywall is going up soon.

Care Center 200 wing is getting tied into the old building. Drywall is going up soon.

024 025

Toilets and fixtures are being installed.

Toilets and fixtures are being installed.

The hospital hallway are coming together nicely.

The hospital hallway are coming together nicely.

057

New exterior doors have been installed.

New exterior doors have been installed.

045

This is an outline of the door to the office.

This is an outline of the door to the office.

054

Cafe is up and the old kitchen is down

Tie-ins have been created to get ready for more progress at the hospital. The cafe area is now used as it was designed, but sections like the utility room, quiet room and old kitchen have been demolished.

Plumbing tie-ins have been created in the new hospital area and is moving along.

Plumbing tie-ins have been created in the new hospital area and is moving along.

The cafe seating area got some tables and chairs and is being used.

The cafe seating area got some tables and chairs and is being used.

The demolition of the old kitchen took no time at all. The kitchen is on the right, and the new hospital wing is on the left. The new ER area will be on the other side of the wall on the left.

The demolition of the old kitchen took no time at all. The kitchen is on the right, and the new hospital wing is on the left. The new ER area will be on the other side of the wall on the left.

Getting ready for plumbing tie-ins. The wall next to the trench is the new hallway from the Care Center to the entrance.

Getting ready for plumbing tie-ins. The wall next to the trench is the new hallway from the Care Center to the entrance.

Cabinets are ready and waiting to be installed.

Cabinets are ready and waiting to be installed.

Patient bathroom progress and old kitchen being demo’d

The changes are happening fast now! You can really tell how the hallway in the Hospital is going to look. The cabinetry for the nutrition center has been added.  We have doors, ceiling grid, sinks, and tile in some of the new patient bathrooms.

013 020 025

The new 200 hallway will become the neighborhood kitchen.

The new 200 hallway will become the neighborhood kitchen.

It didn’t take them very long to demolish the 300 hallway and start work on the plumbing tie-in. Demolition is also proceeding in the kitchen and on the old kitchen wall. They are working on the tie-ins in the hospital and Care Center area.

It didn’t take them very long to demolish the 300 hallway and start work on the plumbing tie-in. Demolition is also proceeding in the kitchen and on the old kitchen wall. They are working on the tie-ins in the hospital and Care Center area.

033 036

Some of the walls are boarded and doors are getting installed.

030 029

New Kitchen Passes Inspection – Open for Business

The Minnesota Department of Health inspected the new hallway and kitchen and were certified for occupancy. With the new hallway open, crews quickly started demolition of the old 300 wing. Signs are appearing around the hallways, routing people to the new hallway. The Chamber of Commerce went on a tour Friday, January 6 of the new areas.

Pass throughs being installed.

Pass throughs being installed in the new hospital’s patient rooms.

Curved radius behind the temporary construction wall.

Curved radius behind the temporary construction wall.

Josh and Scott with Boldt removing the caution tape so we could officially open the new hallway.

Josh and Scott with Boldt removing the caution tape so we could officially open the new hallway.

Gloria Martinea was the first resident to walk down the new hallway. Gloria is a former CCNSHCC employee.

Gloria Martineau was the first resident to walk down the new hallway. Gloria is a former CCNSHCC employee.

Directions routing people to the new hallway.

Directions routing people to the new hallway.

024

Demo of the old 300 wing hallway.

Demo of the old 300 wing hallway.

In the back you can see a brick wall. That is the old kitchen, soon to be the new ER.

In the back you can see a brick wall. That is the old kitchen, soon to be the new ER.

New Kitchen is open for business. In the picture is Wendy Ford, Peggy Brisson, and Kayla Bronikowski.

The new kitchen is open for business. In the picture is Wendy Ford, Peggy Brisson, and Kayla Bronikowski.

New screen in multipurpose room.

New screen in multipurpose room.

Exterior tie-in work between the old building and the new care center 200 wing.

Exterior tie-in work between the old building and the new care center 200 wing.