Care Center is almost ready for Phase 3

Some areas are ready for Phase 3, including the Care Center! Footings for the household kitchen are complete in Phase 3. The former business office is open and the brick walls are torn down as demolition continues. That area will eventually become radiology.

The Care Center now has floors. It's almost ready for Phase 3!

The Care Center now has floors. It’s almost ready for Phase 3!

069 062

Many areas, including ER rooms, pharmacy and a hallway are all studded and ready for drywall.

Many areas, including ER rooms, pharmacy and a hallway are all studded and ready for drywall.

035

The garage has walls, now it just needs a roof.

The garage has walls, now it just needs a roof.

Care Center Wing nearly completed

The parking lot is gone, but that just means there’s more room for progress. The household kitchen has many new additions, and the resident rooms are nearing almost ready to go.

003 015 051

The household kitchen area has cabinets, counter tops, ceiling tiles, and lights.

The household kitchen area has cabinets, counter tops, ceiling tiles, and lights.

The foundation walls are done for the ambulance drive through garage.

The foundation walls are done for the ambulance drive through garage.

Resident rooms are getting final touches.

Resident rooms are getting final touches.

Weathering the weather

Despite the chilly weather conditions, the team is continuing to prepare outside areas for progress. The footings for the ER garage and the employee entrance are completed and the foundation walls have been formed. Inside, many areas now have flooring and paint, including eight resident rooms, kitchen and dining room.

The dining area and the kitchen are now painted.

The dining area and the kitchen are now painted.

The flooring has been installed for all eight resident rooms.

The flooring has been installed for all eight resident rooms.

The kitchen cabinets have arrived!

The kitchen cabinets have arrived!

041

The doors to the new OR/procedure room have been installed, and the OR has been painted.

The doors to the new OR/procedure room have been installed, and the OR has been painted.