Eight patient rooms nearly completed

With March rolling in, it’s out with the old and in with the new emergency department. The floors have been dug up and there’s a wide-open space ready for more progress. Eight patient rooms are almost ready to go, but they will not be used until all the patient rooms and the emergency department is complete.

Almost eight rooms similar to this are completed.

Almost eight rooms similar to this are completed.

059

Some of the walls are now painted in the hallways, offices, and exam areas.

Some of the walls are now painted in the hallways, offices, and exam areas.

The Care Center 200 Wing now has door frames and plumbing tie ins ready for the next step.

The Care Center 200 Wing now has door frames and plumbing tie ins ready for the next step.

The old maintenance shop and kitchen have been dug up and will turn into the emergency department and garage.

The old maintenance shop and kitchen have been dug up and will turn into the emergency department and garage.

Door frames stacked, waiting for walls!

Door frames stacked, waiting for walls!

The floors have been dug up and plumbing tie ins have been made in the new emergency department and the emergency drive-thru.

The floors have been dug up and plumbing tie ins have been made in the new emergency department and the emergency drive-thru.