Moving in supplies and possibly staff this week

The hospital rooms are only missing patients! On the outside, a good part of the retaining wall that separates the front entrance from the building is complete. The third and final phase of the Care Center is coming along, now having underground plumbing finished. With the hopes of good weather, the crew will pour the slab soon and keep working away at the entrance.

 

002 010 012

Hospital rooms have beds, furniture, and supplies.

Hospital rooms have beds, furniture, and supplies.

017

The Emergency Department drive through is finished., storing the new ambulance.

The Emergency Department drive through is finished., storing the new ambulance.

034

The cabinetry and the autoclave have all been installed.

The cabinetry and the autoclave have all been installed.

The CT and power injector have been installed.

The CT and power injector have been installed.

Furniture has arrived for the cafe and waiting area.

Furniture has arrived for the cafe and waiting area.