Care Center is almost ready for Phase 3

Some areas are ready for Phase 3, including the Care Center! Footings for the household kitchen are complete in Phase 3. The former business office is open and the brick walls are torn down as demolition continues. That area will eventually become radiology.

The Care Center now has floors. It's almost ready for Phase 3!

The Care Center now has floors. It’s almost ready for Phase 3!

069 062

Many areas, including ER rooms, pharmacy and a hallway are all studded and ready for drywall.

Many areas, including ER rooms, pharmacy and a hallway are all studded and ready for drywall.

035

The garage has walls, now it just needs a roof.

The garage has walls, now it just needs a roof.

Weathering the weather

Despite the chilly weather conditions, the team is continuing to prepare outside areas for progress. The footings for the ER garage and the employee entrance are completed and the foundation walls have been formed. Inside, many areas now have flooring and paint, including eight resident rooms, kitchen and dining room.

The dining area and the kitchen are now painted.

The dining area and the kitchen are now painted.

The flooring has been installed for all eight resident rooms.

The flooring has been installed for all eight resident rooms.

The kitchen cabinets have arrived!

The kitchen cabinets have arrived!

041

The doors to the new OR/procedure room have been installed, and the OR has been painted.

The doors to the new OR/procedure room have been installed, and the OR has been painted.

Happy spring!

Spring is here, and rooms, hallways and clinics could pass for complete. More areas are getting ready to take shape, including the resident kitchen.

Dr. Mueller's next outreach clinic is almost ready. Equipment has been moved in.

Dr. Mueller’s next outreach clinic is almost ready. Equipment has been moved in.

010

Cafe seating area is now open.

Cafe seating area is now open.

Hospital hallways are coming together.

Hospital hallways are coming together.

048

The walk up to the nurses station.

The walk up to the nurses station.

043 051

This is the former large classroom that was the location of many meetings and educational sessions.

This is the former large classroom that was the location of many meetings and educational sessions.

This was the hallway that led to the kitchen.

This was the hallway that led to the kitchen.

The overhead door for the ER garage is open.

The overhead door for the ER garage is open.

Nurses Station is nearly complete

Major sections like the Nurses Station, the flat roofs over the Care Center, and main hallways are nearly complete. The wall between the ER and the ER garage has also been installed and is coming together.

The junction at the entrance into the Care Center and Hospital is coming together.

The junction at the entrance into the Care Center and Hospital is coming together.

junction2

The Nurses Station has been installed and is almost complete.

The Nurses Station has been installed and is almost complete.

ns2

A new hallway is open and ready to be used.

A new hallway is open and ready to be used.

All of the rooms have been taped and sheetrocked.

All of the rooms have been taped and sheetrocked.

The flat roof over the Care Center is complete.

The flat roof over the Care Center is complete.

Structures are taking shape!

Drywall and door frames are going up, allowing staff to visualize what the inside of the hospital will look like!

The door frames of the doors leading into the hospital are installed.

The door frames of the doors leading into the hospital are installed.

Progress is being made on the hallway and patient rooms.

Progress is being made on the hallway and patient rooms.

Walls have been stood up and MEP rough-in has started.

Walls have been stood up and MEP rough-in has started.

Care Center 200 hall is coming together.

Care Center 200 hall is coming together.

The central area will be the outreach clinic space.

The central area will be the outreach clinic space.